Progress rate of site transfer to the investor in Dong Nai River Project to be promoted

Posted Date: 15/08/2011
On the morning of July 26, Vice-Chairman of the provincial People Committee Dinh Quoc Thai chaired the meeting with relevant departments, branches and sectors on implementation of compensation, resettlement support, site transfer in New Dong Nai Bridge Project and routes to two bridge heads in Bien Hoa city area. Vice-Chairman of the provincial People Committee Tran Van Vinh also attended it.
The meeting view

According to Bien Hoa City Land Fund Development Center, the total area that has been retrieved for the implementation of this project is 173,549 kilometers, with total length of 1,900 meters, passing two wards, An Binh and Long Binh Tan, involving 17 organizations and 295 households in the clearance status. For the time being, in Long Binh ward, it has finished compensation, resettlement for households with whole cleared site and transfer of the whole site to the investor as set plan and progress rate.  

 In Long Binh Tan ward alone, 50 households are having trouble with the 51 National Road Expansion project; the seven-meter boundary that has been retrieved before it has not been determined, thereby having no foundation to set the price. Up to now, the total area that has been transferred to the investor if 4,268 meters.

  Also at the meeting, Chairman of the provincial People’s Committee Dinh Quoc Thai requested that departments and sectors check over and propose support rate for the case of wrong use with provided land and promote site progress rate for the investor.

Reported by Dieu Linh, translated by Hoai Thu