Traffic works in Dong Nai province still implemented slowly

Posted Date: 15/09/2009
On the morning of May 19, 2009, Vice Chairman of the Provincial People’s Committee Tran Van Vinh had a working session with related department and sectors to discuss traffic works in Dong Nai province, then to solve some problems in the period of project implementation.
HTML clipboard


          According to the report made by Dong Nai Transport Department, due to some shortcomings in site clearance, the traffic works in Dong Nai province were still implemented slowly compared to the set plan. The investment phrase now continues to be speeded up to deploy the projects in 2009.

 

Vice Chairman Tran Van Vinh at the working session on traffic works in Dong Nai province

 

After hearing report from Dong Nai Department of Transport, Vice Chairman Tran Van Vinh commented that the plans for traffic works were not practical, so the implementation process did not meet the demand. No projects has been finished now, thus he suggested that Dong Nai Department of Finance should make a plan in which districts are advanced some specific funds to carry out site clearance for residents, and the districts have to complete project documents that are submitted to the provincial People’s Committee in the shortest time (first week of June).

Additionally, some districts reported that land surveying has some mistakes that lead to regular land occupation, and then the bench mark has to be relocated at the beginning. As for this problem, Vice Chairman Tran Van Vinh suggested that the Office of the provincial People’s Committee should hold a meeting next week to solve the problem more clearly with the Measuring Centre and Dong Nai Department of Natural Resources and Environment.

Reported by Thao Que, Translated by Minh Minh