Representatives of the work execution unit report progress rate of land clearance compensation. |
According to VEC, over the past time, districts that the highway passes have concentrated on implementing land clearance compensation. By now, Nhon Trach district, Long Thanh district, Cam My district, Thong Nhat district finished 100%, 65.8%, 94.9%, over 98% of land clearance respectively.
Addressing the meeting, the Vice-Chairperson of the provincial People’s Committee Dinh Quoc Thai requested, to speed up land clearance of road passing Long Thanh district, the investor should directly work with localities quickly and specifically to find the most suitable solutions. Moreover, water supply and drainage for the project need to be deployed in a short time, ensuring the work progress rate.
Reported by T.Q, translated by Hoai Thu.