Vice-Chairman Dinh Quoc Thai chaired the working session |
According to the report of Dong Nai General Hospital, till June 10, 2010, the project was completed for bid package of drilled pier and currently waiting to be checked.
Since June 2, 2010, the Hospital has made selection of consultant contractors for tender of the first bid package, completed and signed contracts with bidding consultant units on June 10, 2010. Under the plan proposed by the end of October, 2010, the hospital will finish and pass bid results and sign construction contracts.
Giving a speech in the meeting, Vice Chairman Dinh Quoc Thai requested investors and the managerial board of the project need to consider reasonable time, reduce the unnecessary time, extend time for investors to study the project, because this is an important work to be really concerned by leaders and all people of the provinc.
Reported by Thao Que, translated by Hoai Thu