Some shortcomings of land clearance and compensation for high-rise apartment building in Quang Vinh ward
Posted Date: 20/07/2011
On May 13, the Provincial People’s Committee held a meeting to report the process of site clearance and compensation for the high-rise apartment building project in Nguyen Van Troi street, Quang Vinh ward. The meeting was presided by Vice Chairman of the Provincial People’s Committee Dinh Quoc Thai.
HTML clipboard
 |
|
Compensation Council of Nguyen Van Troi high-rise apartment building
project |
|
The project (Zone B) has a revoked land area of
29,524.5m2 with 24 project-affected households. Of which, 20 households received
compensation money (one household was supported with the land price in 2008). 19
households transferred their land to the project’s contractor with a total area
of 24,440.2m2. However, the implementation of the project has met some
difficulties. Some households involved did not agree to transfer their lands to
the contractor, because they want to require compensation based on the land
prices of 2008 and need to be resettled. Accordingly, Compensation Council
collaborated with House Trading Joint Stock Company to unanimously approve the
compensation level based on the land prices in 2008 for 5 households who have
not received compensation yet. 4 households have not so far received
compensation yet. As for resettlement, all households involved did not meet
requirements of resettlement according to regulations.
At the meeting, Vice Chairman Dinh Quoc Thai
suggested that the Compensation Council and House Trading Joint Stock Company
must cooperate to solve remaining problems in order to carry out the project as
scheduled.
Reported by N. Thuong, Translated by Minh Minh